header-bg
-- documents Feed--
-- All of Bhamgov Feed --

Current Construction Projects

Print this page
Text resize increase font size decrease font size
Planned Projects for the 2023 Construction Season

2023 is looking to be a very busy year for construction in Birmingham. There are some projects
from 2022 that are scheduled to be finished this spring as soon as weather conditions allow,
followed by this years’ planned capital projects. Note that all projects are subject to City
Commission approval and budget constraints.

FY22_23CIP

CONTINUING PROJECTS FROM 2022:

2022 Cape Seal Program
Design has been completed for cape-seal treatment on Taunton between Woodward and Lincoln, Torry
between Emmons and Sheffield, Bradford between Sheffield and Eton, Croft between Bradford and 14
Mile Road, Penistone between Torry and 14 Mile Road, Banbury between Torry and Sheffield,
Humphrey between Torry and Eton, and Melton between Taunton to Eton. The existing unimproved
road surface will be restored with a new cape-seal treatment as part of the unimproved street
maintenance program. Work is tentatively scheduled to begin in 2023 Spring.  The project was awarded to Highway Maintenance and Construction for the lowest bid of $421,587.10.

The Special Assessment for each property can be found in the linked MEMO below:
  1. Cape Seal 2022 SAD


View the commission meeting minutes of the awarded project from September 19th, 2022:
  1. Public Hearing for 2022 Cape Seal Program, Hearing of Necessity for Special Assessment District PAGE 3
  2. Confirming SAD Roll Page 3
Sewer Rehabilitation Program
This project includes sewer rehabilitation services to clean and inspect certain sewer
segments throughout the City. Work items for rehabilitating minor sewer issues that
may be found, such as removal of roots, grinding mineral deposits, grouting leaking
joints, and limited internal patching of holes and open joints. The
contractor for this project is DVM Utilities and work is continuing on this project to improve the sewer system.

Parking Lot #5 Slope Repair

Design is underway for slope stability and erosion control measures to stabilize the slope
along the northern edge of lot #5. Excessive rain events that overwhelm the storm
sewer catch basins has resulted in deterioration of the slope that extends down to the
Rouge River from the north end of the parking lot. This work will have to be
coordinated with the planned asphalt pavement repairs in the parking lot.

2022 Concrete Sidewalk Program
The 2022 sidewalk repairs program will focus on Residential Area 5 and Downtown
Area 1C. Area 5 extends in general from Southfield Rd to the western City limits, and
Maple Rd to the southern City limits14 Mile Road. Area 1C of the downtown generally
extends from Woodward to Pierce, from Maple Road to Daines. Construction on this
work would likely begin in late summer.


NEW TO 2023

Brown Street: S. Old Woodward Ave. to Woodward Ave.
Reduce the roadway to three lanes, improve pedestrian traffic and turning movements, and minor street scape improvements.

BrownSt_Overview

Pierce Street, 14 Mile Road to Lincoln Street
Replacing the existing 6-inch water main on the east side of the street from Lincoln Street to 14 Mile Road, ADA ramp upgrades, full-depth road reconstruction for trench end excavations, and other road repair sections.

Lincoln Hills Golf Course Tee No. 1 
Improvements to the cart path, retaining walls, and staircase to Tee No. 1 are currently out for bids. 

Cranbrook Non-Motorized Shared Use Path (TAP Grant)
Design work has started for constructing a new 10-ft wide shared use path along
Cranbrook, from 14 Mile to Midvale, and new sidewalk along the north side of 14 Mile,
from Cranbrook to the western City limits, and on the south side of Lincoln, from
Cranbrook to Golfview. This project will likely start later in the summer, with completion
in the fall.

Water Tower Maintenance and Coating
Necessary repairs and maintenance work will be performed on both water towers,
including replacing the coatings (paint) on the exterior and interior of the tanks. Project will be bid in Fall
2022 with construction starting in Spring of 2023.

Unimproved Streets
With the City Commission’s approval of the policy modifications related to initiation of
street improvement projects, the Engineering Department is planning to initiate design
of a water and sewer improvement project to be constructed in 2023 on the following unimproved
streets:
• Westwood Drive, Raynale St. to Oak St. including:
• Oak St., N. Glenhurst Dr. to western City Limits
• Raynale St., N. Glenhurst Dr. to western City Limits

Planned Projects for the 2024 Construction Season

The public is invited to attend a South Eton Construction Project Open House event on Tuesday, January 17, 2023 from 6:30 p.m. – 8:30 p.m. at the Department of Public Services, located at 851 South Eton. Attendees may park inside the gate and use the side entrance. The construction project will take place on South Eton Street between 14 Mile Road and Yosemite Boulevard beginning in the spring of 2024.

Event attendees will learn how to participate in an upcoming survey as city planners and engineers kick off planning for the 2024 project. A variety of design concepts will be on display and attendees may come and go at any time throughout the event.

Representatives from the city’s design consultant, MKSK, will be in attendance and available to discuss design concepts with attendees. MKSK is a collective of planners, urban designers and landscape architects based out of Detroit. MKSK previously worked with the City of Birmingham on projects such as the three award-winning phases of infrastructure improvements throughout the downtown area.